Ive got a tiling job to do for the inlaws. Its in a room thats had a new floor laid after the old one crumbled and lifted due to a problem with ash content in the old floor.
It was dug out to get rid of all the ash (800 mm) then hardcore, concrete and finally a screed to finish it off. The work was done by a mate of mine who's a builder and he told me to leave it 5 weeks or so before tiling.
After the 5 weeks can i just tile straight onto the new screed or is there anything i should do first, preperationwise.
Thanks in advance,
Fred.
Tiling on a brand new floor
Moderator: Moderators
-
- Senior Member
- Posts: 6620
- Joined: Sun Jan 24, 2010 1:48 pm
- Location: Essex
- Has thanked: 39 times
- Been thanked: 621 times
5 weeks is fine for screed but concrete needs 7 weeks......just thought I would chuck that in.
Anyway......safest bet is to go with Bal Green Screed Adhesive. reason being that if the moisture content is still a bit high, and without a meter you won't know, this product is specifically designed to cope. Infact you can tile onto screed with this after just 2 days drying.
Anyway......safest bet is to go with Bal Green Screed Adhesive. reason being that if the moisture content is still a bit high, and without a meter you won't know, this product is specifically designed to cope. Infact you can tile onto screed with this after just 2 days drying.
-