Re: Double side extension 2012:- 53sq metres of floor
Hi all
Got all upstairs ceilings boarded in the last day or so, got a week off now to really get this place sorted for the plasterer, lots of bits to do to get it sorted so could be a few long days coming
Pictures to follow in the next few days.....
Thank you
Got all upstairs ceilings boarded in the last day or so, got a week off now to really get this place sorted for the plasterer, lots of bits to do to get it sorted so could be a few long days coming
Pictures to follow in the next few days.....
Thank you
-
- Senior Member
- Posts: 267
- Joined: Sun Dec 11, 2011 2:36 pm
- Has thanked: 41 times
- Been thanked: 5 times
Re: Double side extension 2012:- 53sq metres of floor
Evening All
A little bit of plasterboard on the walls and ceilings, much better than looking at the blockwork
2 bedrooms and the kitchen started, the big push now thou is to get all the kitchen finished ready for plastering within the next week or two, i also need the BI back this week to pass off the steelwork structures and insulation etc..
Finalised the kitchen design this morning, a very painful day
i will try and upload a picture of the kitchen design tomorrow...
Thanks for following the thread, really pleased to see we have now reached 10,000 views, hope people are picking up some tips along the way
A little bit of plasterboard on the walls and ceilings, much better than looking at the blockwork
2 bedrooms and the kitchen started, the big push now thou is to get all the kitchen finished ready for plastering within the next week or two, i also need the BI back this week to pass off the steelwork structures and insulation etc..
Finalised the kitchen design this morning, a very painful day
i will try and upload a picture of the kitchen design tomorrow...
Thanks for following the thread, really pleased to see we have now reached 10,000 views, hope people are picking up some tips along the way
- Attachments
-
- Kitchen with boarding started..
- House Extension 2012 001 (Small).JPG (128.26 KiB) Viewed 3330 times
-
- Kitchen
- House Extension 2012 003 (Small).JPG (121.09 KiB) Viewed 3330 times
-
- House Extension 2012 004 (Small).JPG (135.64 KiB) Viewed 3330 times
-
- House Extension 2012 005 (Small).JPG (106.66 KiB) Viewed 3330 times
-
- House Extension 2012 006 (Small).JPG (107.9 KiB) Viewed 3330 times
-
- House Extension 2012 007 (Small).JPG (121.52 KiB) Viewed 3330 times
-
- Senior Member
- Posts: 267
- Joined: Sun Dec 11, 2011 2:36 pm
- Has thanked: 41 times
- Been thanked: 5 times
Re: Double side extension 2012:- 53sq metres of floor
Great pal isn't it, wish that's all there was on my list for the new kitchen, that would keep the cost downroot wrote:loving the minimalist kitchen
-
- Senior Member
- Posts: 267
- Joined: Sun Dec 11, 2011 2:36 pm
- Has thanked: 41 times
- Been thanked: 5 times
Re: Double side extension 2012:- 53sq metres of floor
Yeeeeaaaaaahhhhh I have daylight back in my kitchen....
The bi folding door is 99% finished, photos to follow tomorrow, looks fantastic
-
- Senior Member
- Posts: 267
- Joined: Sun Dec 11, 2011 2:36 pm
- Has thanked: 41 times
- Been thanked: 5 times
Re: Double side extension 2012:- 53sq metres of floor
Afternoon all
Had a busy week and managed to pull things along a bit, more plaster boarding done, Bi fold doors in, plyed the ceiling near the velux in the kitchen, re routed the water from the bathroom wastes across the steel work and out the gable end, kitchen ordered today and collected the fire door, so plenty done
here we go anyway...some more photo's
Had a busy week and managed to pull things along a bit, more plaster boarding done, Bi fold doors in, plyed the ceiling near the velux in the kitchen, re routed the water from the bathroom wastes across the steel work and out the gable end, kitchen ordered today and collected the fire door, so plenty done
here we go anyway...some more photo's
- Attachments
-
- House Extension 2012 009 (Small).JPG (122.81 KiB) Viewed 3242 times
-
- House Extension 2012 008 (Small).JPG (127.38 KiB) Viewed 3242 times
-
- House Extension 2012 007 (Small).JPG (165.2 KiB) Viewed 3242 times
-
- and the door in the day light
- House Extension 2012 006 (Small).JPG (164.52 KiB) Viewed 3242 times
-
- House Extension 2012 005 (Small).JPG (128.83 KiB) Viewed 3242 times
-
- The Door in
- House Extension 2012 004 (Small).JPG (157.35 KiB) Viewed 3242 times
-
- House Extension 2012 003 (Small).JPG (166.88 KiB) Viewed 3242 times
-
- Triangulation started also in the kitchen
- House Extension 2012 002 (Small).JPG (141.65 KiB) Viewed 3242 times
-
- House Extension 2012 001 (Small) (2).JPG (166.07 KiB) Viewed 3242 times
-
- Senior Member
- Posts: 267
- Joined: Sun Dec 11, 2011 2:36 pm
- Has thanked: 41 times
- Been thanked: 5 times
Re: Double side extension 2012:- 53sq metres of floor
Morning All
A week of mainly joinery and further plaster boarding, just half a day away from all plasterboarding downstairs being completed
All door casings now in place, but the downstairs kitchen was an absolute nightmare as it was going back into the original doorway from when the house was built, it was all out of line with anything the joiner tried to line up with and well after a day at it the joiner made an absolute fantastic job of it
Also got the fire door in between the garage and the kitchen, bloody heavy lifting that about
I also got the cavity insulations in place at rear bi folding doors and the side of the kitchen/garage fire door.
Next week we move on to the plastering of the kitchen and maybe the downstairs w/c (the old kitchen entrance where the boiler used to hung on the wall) expecting this to take around 4 days, on a tight schedule now as the kitchen is due to be started to be fitted the Tuesday the week after Nothing can run over or the wife will kill me
Thanks for following and more up dates next week..
Cheers
A week of mainly joinery and further plaster boarding, just half a day away from all plasterboarding downstairs being completed
All door casings now in place, but the downstairs kitchen was an absolute nightmare as it was going back into the original doorway from when the house was built, it was all out of line with anything the joiner tried to line up with and well after a day at it the joiner made an absolute fantastic job of it
Also got the fire door in between the garage and the kitchen, bloody heavy lifting that about
I also got the cavity insulations in place at rear bi folding doors and the side of the kitchen/garage fire door.
Next week we move on to the plastering of the kitchen and maybe the downstairs w/c (the old kitchen entrance where the boiler used to hung on the wall) expecting this to take around 4 days, on a tight schedule now as the kitchen is due to be started to be fitted the Tuesday the week after Nothing can run over or the wife will kill me
Thanks for following and more up dates next week..
Cheers
- Attachments
-
- The finished triangulation for the single storey kitchen roof.
- House Extension 2012 009 (Small).JPG (120.44 KiB) Viewed 3151 times
-
- Door casings for new kitchen door entry
- House Extension 2012 010 (Small).JPG (119.79 KiB) Viewed 3151 times
-
- Fire door and frame now in place
- House Extension 2012 006 (Small).JPG (116.62 KiB) Viewed 3151 times
-
- Cavity closures in place
- House Extension 2012 005 (Small).JPG (114.76 KiB) Viewed 3151 times
-
- New kitchen door in place with casings on, to the left of that a little bit of plasterboarding to finish, behing there will be the downstairs W\C.
- House Extension 2012 008 (Small).JPG (126.99 KiB) Viewed 3151 times
-
- Steel supports nearly fully boarded, require a couple of layers for fire safety
- House Extension 2012 007 (Small).JPG (109.77 KiB) Viewed 3151 times
-
- Senior Member
- Posts: 16996
- Joined: Fri Jan 20, 2006 5:51 pm
- Location: Essex
- Has thanked: 814 times
- Been thanked: 3508 times
Re: Double side extension 2012:- 53sq metres of floor
It is coming along nicely, you are well on the way now. Just boarding out makes a major leap forward and once you start installing kitchen units you hit a significant point. Just remember that it is all the finishing that takes time and you are so dog tired of it all it is easy to slide and ruin the ship for a ha'penny of tar.
Well done so far mate
DWD
Well done so far mate
DWD
-
- Senior Member
- Posts: 267
- Joined: Sun Dec 11, 2011 2:36 pm
- Has thanked: 41 times
- Been thanked: 5 times
Re: Double side extension 2012:- 53sq metres of floor
Evening all
Sorry for the delay in updating but been a little busy, all kitchen now fully plastered, electrics all in place ready, kitchen ready to be fitted Thursday, new bar stools and accessories purchased, laminate floor and under lay purchased, stud wall joinery work done in upstairs bedrooms to make it easier to board out, frame in downstairs wc in progress in order to box in electric cables and meter, rear outside double hopper fitted to take all rain water,shower,bath and sink waste plus washer,sink and dishwasher waste from kitchen area.
The appliance Sockets now have nice plastic fittings attached ready for the appliances to be plugged in soon a kitchen back, I cannot wait, eating for the last 4 weeks is taking its toll all ways round
Going forward kitchen starts to be fitted Thursday, porch and garage roof now started to the front, laminate to go down middle of next week, painter arriving shortly after....
Things really motoring, I may just may scrape it being done by Christmas, but still things to do
Pictures will be updated Friday as this is the first chance I will have.
Sorry for the delay...
Cheers
Sorry for the delay in updating but been a little busy, all kitchen now fully plastered, electrics all in place ready, kitchen ready to be fitted Thursday, new bar stools and accessories purchased, laminate floor and under lay purchased, stud wall joinery work done in upstairs bedrooms to make it easier to board out, frame in downstairs wc in progress in order to box in electric cables and meter, rear outside double hopper fitted to take all rain water,shower,bath and sink waste plus washer,sink and dishwasher waste from kitchen area.
The appliance Sockets now have nice plastic fittings attached ready for the appliances to be plugged in soon a kitchen back, I cannot wait, eating for the last 4 weeks is taking its toll all ways round
Going forward kitchen starts to be fitted Thursday, porch and garage roof now started to the front, laminate to go down middle of next week, painter arriving shortly after....
Things really motoring, I may just may scrape it being done by Christmas, but still things to do
Pictures will be updated Friday as this is the first chance I will have.
Sorry for the delay...
Cheers
-
- Senior Member
- Posts: 267
- Joined: Sun Dec 11, 2011 2:36 pm
- Has thanked: 41 times
- Been thanked: 5 times
Re: Double side extension 2012:- 53sq metres of floor
Hi Prem
The kitchen has come from Sheffield kitchen Outlet, my mum and sister had there kitchen from here and they are sound people, even my joiner told me he buys everything through them as they are great quality which was nice to hear
Pictures below, sorry for the delay
I will get myself sorted with the pics, slacking a little...
Cheers for watching....
The kitchen has come from Sheffield kitchen Outlet, my mum and sister had there kitchen from here and they are sound people, even my joiner told me he buys everything through them as they are great quality which was nice to hear
Pictures below, sorry for the delay
I will get myself sorted with the pics, slacking a little...
Cheers for watching....
-
- Senior Member
- Posts: 267
- Joined: Sun Dec 11, 2011 2:36 pm
- Has thanked: 41 times
- Been thanked: 5 times
Re: Double side extension 2012:- 53sq metres of floor
Right guys and girls, pics earlier than expected, took an early day today as these long days are catching up with me
More to follow in next few days, Porch blockwork tidied up today ready for the roof work to begin.....
Bed time now
More to follow in next few days, Porch blockwork tidied up today ready for the roof work to begin.....
Bed time now
- Attachments
-
- More joinery in the WC
- House Extension 2012 008 (Small).JPG (113.38 KiB) Viewed 2958 times
-
- Joinery in what will be the downstairs WC, put in place to ensure all the wiring and elecy meeting will be covered up
- House Extension 2012 007 (Small).JPG (118.95 KiB) Viewed 2958 times
-
- Kitchen all ready to be fitted, little room to move to be honest thou, fitting starts tomorrow 8am Promt:)
- House Extension 2012 005 (Small).JPG (132.24 KiB) Viewed 2958 times
-
- Stripped back to ensure all the kitchen looks perfect, this was the only original wall left from the original kitchen, so it looked a little rough to be honest...
- House Extension 2012 004 (Small).JPG (144.05 KiB) Viewed 2958 times
-
- A little more plastering
- House Extension 2012 003 (Small).JPG (136.74 KiB) Viewed 2958 times
-
- Other wall of kitchen plastered and well on the way to drying
- House Extension 2012 002 (Small).JPG (131.06 KiB) Viewed 2958 times
-
- Plaster boarding around the triangulation
- House Extension 2012 001 (Small).JPG (116.32 KiB) Viewed 2958 times
-
- Senior Member
- Posts: 267
- Joined: Sun Dec 11, 2011 2:36 pm
- Has thanked: 41 times
- Been thanked: 5 times
Re: Double side extension 2012:- 53sq metres of floor
Afternon All
Well here we go the kitchen fit is under way
Porch has also now been started
Well here we go the kitchen fit is under way
Porch has also now been started
- Attachments
-
- Still this lot to fit thou.........
- House Extension 2012 002 (Small).JPG (131.95 KiB) Viewed 2922 times
-
- Kitchen partly in place....
- House Extension 2012 001 (Small).JPG (124 KiB) Viewed 2922 times
-
- Senior Member
- Posts: 267
- Joined: Sun Dec 11, 2011 2:36 pm
- Has thanked: 41 times
- Been thanked: 5 times
Re: Double side extension 2012:- 53sq metres of floor
A little more progress with the Island now in place, time to order the granite £££££
Also a little pic of the rear double hopper now in place.
Cheers
Also a little pic of the rear double hopper now in place.
Cheers
- Attachments
-
- House Extension 2012 003 (Small).JPG (160.23 KiB) Viewed 2907 times
-
- House Extension 2012 002 (Small).JPG (121.17 KiB) Viewed 2907 times
-
- House Extension 2012 001 (Small).JPG (123 KiB) Viewed 2907 times