Double side extension 2012:- 53sq metres of floor area
Moderator: Moderators
-
- Senior Member
- Posts: 267
- Joined: Sun Dec 11, 2011 2:36 pm
- Has thanked: 41 times
- Been thanked: 5 times
Re: Double side extension 2012:- 53sq metres of floor
Evening All on this snowy cold evening
A quick update on the outside works...
Porch and garage roof now on including the lead work, all guttering in place, just down pipes to fit and connect, under ground pipework connected across front of porch to the main drains sited at front of garage,added a rodding eye just in case along with a little bit of drainage in front of the garage, this has just been put in place in case we apply for planning for the drive to block pave or something simular as the drive runs downhill towards the garage door entrance, dont want no flooding in my new garage
Managed to get the porch door and window in place today, not finished but you get the picture.
Next week the Electrical insulated Garage door is to be fitted another less draft.
Not long till we pour the concrete for the garage floor, may need to be a little bit warmer, but TBH it is under cover and not under the direct effect of the frost....
Here we go some pictures for you all.... the best bit
A quick update on the outside works...
Porch and garage roof now on including the lead work, all guttering in place, just down pipes to fit and connect, under ground pipework connected across front of porch to the main drains sited at front of garage,added a rodding eye just in case along with a little bit of drainage in front of the garage, this has just been put in place in case we apply for planning for the drive to block pave or something simular as the drive runs downhill towards the garage door entrance, dont want no flooding in my new garage
Managed to get the porch door and window in place today, not finished but you get the picture.
Next week the Electrical insulated Garage door is to be fitted another less draft.
Not long till we pour the concrete for the garage floor, may need to be a little bit warmer, but TBH it is under cover and not under the direct effect of the frost....
Here we go some pictures for you all.... the best bit
- Attachments
-
- House Extension 2012 010 (Small).JPG (121.51 KiB) Viewed 5815 times
-
- In place, sorry its dark on the picture finished about 17.15pm
- House Extension 2012 009 (Small).JPG (120.3 KiB) Viewed 5815 times
-
- Porch door ready to go in...
- House Extension 2012 008 (Small).JPG (118.9 KiB) Viewed 5815 times
-
- Porch frame ready to go...
- House Extension 2012 007 (Small).JPG (139.55 KiB) Viewed 5815 times
-
- In place in case we block pave or simular
- House Extension 2012 004 (Small).JPG (175.06 KiB) Viewed 5815 times
-
- Pipework running under the temp steps towards garage
- House Extension 2012 006 (Small).JPG (182 KiB) Viewed 5815 times
-
- In place for guttering connection...
- House Extension 2012 005 (Small).JPG (174.35 KiB) Viewed 5815 times
-
- House Extension 2012 003 (Small).JPG (153.66 KiB) Viewed 5815 times
-
- Porch roof on along with the lead..
- House Extension 2012 002 (Small).JPG (162.88 KiB) Viewed 5815 times
-
- Guttering in place
- House Extension 2012 001 (Small).JPG (165.11 KiB) Viewed 5815 times
-
- Senior Member
- Posts: 267
- Joined: Sun Dec 11, 2011 2:36 pm
- Has thanked: 41 times
- Been thanked: 5 times
Re: Double side extension 2012:- 53sq metres of floor
Evening All
A quick up date, front porch door on and sealed, downpipes for porch and garage rain water in place, rodding eye fixed in place, Electric insulated garage door on and working
Hoping to get the garage floor levelled and concreted next week, plus another tidy up required as i still have the scaffolders scaffold in my back garden some 6 months since i dropped the last bit they said they would come back for
Then i will be ready for the front steps to be put in place to the porch entry, plus the steps in the garage to give access to the kitchen.
Still internal bits to tidy up like window sills in the bedrooms and some plasterboarding and insulating in porch etc but we are back moving along in this cold weather
Thanks
A quick up date, front porch door on and sealed, downpipes for porch and garage rain water in place, rodding eye fixed in place, Electric insulated garage door on and working
Hoping to get the garage floor levelled and concreted next week, plus another tidy up required as i still have the scaffolders scaffold in my back garden some 6 months since i dropped the last bit they said they would come back for
Then i will be ready for the front steps to be put in place to the porch entry, plus the steps in the garage to give access to the kitchen.
Still internal bits to tidy up like window sills in the bedrooms and some plasterboarding and insulating in porch etc but we are back moving along in this cold weather
Thanks
- Attachments
-
- Rodding eye put in place just in case:( hopefully never required...
- House Extension 2012 003 (Small).JPG (164.11 KiB) Viewed 5741 times
-
- More downpipe and Hopper in place..
- House Extension 2012 004 (Small).JPG (137.77 KiB) Viewed 5741 times
-
- Drainage in place, just in case i get some money to make a hard standing,planning required...
- House Extension 2012 002 (Small).JPG (160.57 KiB) Viewed 5741 times
-
- Front garage door and porch door along with downpipe in place.
- House Extension 2012 001 (Small).JPG (146.78 KiB) Viewed 5741 times
-
- Inside of garage door
- House Extension 2012 005 (Small).JPG (140.97 KiB) Viewed 5741 times
-
- Senior Member
- Posts: 267
- Joined: Sun Dec 11, 2011 2:36 pm
- Has thanked: 41 times
- Been thanked: 5 times
Re: Double side extension 2012:- 53sq metres of floor
Sorry a picture needs rotating, i hate seeing pictures the wrong way round, here we again, sorry.
- Attachments
-
- The downpipe and hopper... the right way round this time
- House Extension 2012 004 (Small).JPG (150.17 KiB) Viewed 5741 times
-
- Newly registered Member
- Posts: 12
- Joined: Mon Dec 28, 2009 3:34 pm
- Location: Newcastle-upon-Tyne
- Has thanked: 3 times
- Been thanked: 1 time
Re: Double side extension 2012:- 53sq metres of floor
Didn't know you could get insulated garage doors, are they much more expensive? What the total start time to expected finish time then Walchy?
-
- Senior Member
- Posts: 267
- Joined: Sun Dec 11, 2011 2:36 pm
- Has thanked: 41 times
- Been thanked: 5 times
Re: Double side extension 2012:- 53sq metres of floor
Hi therewolfwiser wrote:Didn't know you could get insulated garage doors, are they much more expensive? What the total start time to expected finish time then Walchy?
Yes insulated garage door, if you have looked through the thread and see how much insulation has been put in the building it was a no brainier for me, my garage leads straight into my kitchen, so another draft less was my view, yes was a little more expensive I think the difference was £130 for insulated....
I am hoping everything will be done and completed by end of April 2013 this is to include the rear decking also.
More snow has not helped again but as it has delayed a few bits but still full steam ahead...
Thanks and hope that answers your questions...
Cheers
-
- Senior Member
- Posts: 267
- Joined: Sun Dec 11, 2011 2:36 pm
- Has thanked: 41 times
- Been thanked: 5 times
Re: Double side extension 2012:- 53sq metres of floor
Hi All
Quick update...
Porch ceiling insulated,tv bracket and tv on the wall along with a shelf.
Garage cleared out, concrete poured and levelled.
Window surround around new window plastered all ready for painter next week.
Scaffold ready to be moved away...
Plasterer back Monday to board out porch and downstairs WC...
Things coming together now..
Cheers more updates later next week...
Thanks
Quick update...
Porch ceiling insulated,tv bracket and tv on the wall along with a shelf.
Garage cleared out, concrete poured and levelled.
Window surround around new window plastered all ready for painter next week.
Scaffold ready to be moved away...
Plasterer back Monday to board out porch and downstairs WC...
Things coming together now..
Cheers more updates later next week...
Thanks
- Attachments
-
- Dining room that adjoins the kitchen ready for patching up, this damage was caused in order to get the steelwork in place..
- House Extension 2012 001 (Small).JPG (116.63 KiB) Viewed 5586 times
-
- House Extension 2012 009 (Small).JPG (119.76 KiB) Viewed 5586 times
-
- House Extension 2012 008 (Small).JPG (154.19 KiB) Viewed 5586 times
-
- House Extension 2012 003 (Small).JPG (175.9 KiB) Viewed 5586 times
-
- Scaffold ready to be moved into the front for collection.
- House Extension 2012 012 (Small).JPG (133.38 KiB) Viewed 5586 times
-
- House Extension 2012 014 (Small).JPG (154.17 KiB) Viewed 5586 times
-
- House Extension 2012 016 (Small).JPG (132.85 KiB) Viewed 5586 times
-
- Senior Member
- Posts: 267
- Joined: Sun Dec 11, 2011 2:36 pm
- Has thanked: 41 times
- Been thanked: 5 times
Re: Double side extension 2012:- 53sq metres of floor
Morning All
Short Up date on this weeks progress...
Porch walls and ceilings plaster boarded and plastered, still drying ,Downstairs WC all plasterboarded and plastered too, Original dining room wall filled and plastered ready for painting...
Bi Folding doors now fully open and close and lock as they should, something we put off until we had a full clear day to concentrate on correcting, now done
Thanks for watching,more next week, steps to be built in garage and at porch door, plus painting begins Tuesday all of the upstairs extension, if i can may get porch and wc done too will have to get a shifty on thou
End of month all the bathroom fittings will get fitted, Tiolet,sink and vanity unit, plus shower tray and cubicle, and towel radiator, also may get downstairs wc toilet and sink in and towel rad too.. busy month..
Cheers
Short Up date on this weeks progress...
Porch walls and ceilings plaster boarded and plastered, still drying ,Downstairs WC all plasterboarded and plastered too, Original dining room wall filled and plastered ready for painting...
Bi Folding doors now fully open and close and lock as they should, something we put off until we had a full clear day to concentrate on correcting, now done
Thanks for watching,more next week, steps to be built in garage and at porch door, plus painting begins Tuesday all of the upstairs extension, if i can may get porch and wc done too will have to get a shifty on thou
End of month all the bathroom fittings will get fitted, Tiolet,sink and vanity unit, plus shower tray and cubicle, and towel radiator, also may get downstairs wc toilet and sink in and towel rad too.. busy month..
Cheers
- Attachments
-
- WC plasterboarded
- House Extension 2012 003 (Small).JPG (117.01 KiB) Viewed 5497 times
-
- porch more plasterboard
- House Extension 2012 002 (Small).JPG (120.2 KiB) Viewed 5497 times
-
- Porch plaster boarded
- House Extension 2012 001 (Small).JPG (115.43 KiB) Viewed 5497 times
-
- More plastic window ledge..
- House Extension 2012 005 (Small).JPG (152.47 KiB) Viewed 5497 times
-
- Plastic window ledge in place
- House Extension 2012 006 (Small).JPG (123 KiB) Viewed 5497 times
-
- WC plastered
- House Extension 2012 007 (Small).JPG (116.1 KiB) Viewed 5497 times
-
- WC plastered
- House Extension 2012 008 (Small).JPG (100 KiB) Viewed 5497 times
-
- Dinig room patched up ready for paint..
- House Extension 2012 009 (Small).JPG (100.19 KiB) Viewed 5497 times
-
- House Extension 2012 010 (Small).JPG (125.96 KiB) Viewed 5497 times
-
- House Extension 2012 011 (Small).JPG (126.88 KiB) Viewed 5497 times
-
- Senior Member
- Posts: 267
- Joined: Sun Dec 11, 2011 2:36 pm
- Has thanked: 41 times
- Been thanked: 5 times
Re: Double side extension 2012:- 53sq metres of floor
Afternoon All
Quick up date, been a bit slow recently as i have had a months wait on my en suite fittings, toilet,sink,vanity units,taps etc..
Anyway, all upstairs now painted and even managed to get the front steps and garage steps in place....
Downstairs wc painted and the porch painted too
Managed to get all soil wastes in place ready for en suite and WC, pipework in place ready to connect everything up in the en suite.
Alarm PIR added in the Kitchen and the garage..
Further up dates once i get the en suite and wc underway...
Quick up date, been a bit slow recently as i have had a months wait on my en suite fittings, toilet,sink,vanity units,taps etc..
Anyway, all upstairs now painted and even managed to get the front steps and garage steps in place....
Downstairs wc painted and the porch painted too
Managed to get all soil wastes in place ready for en suite and WC, pipework in place ready to connect everything up in the en suite.
Alarm PIR added in the Kitchen and the garage..
Further up dates once i get the en suite and wc underway...
- Attachments
-
- Main bedroom painted part 2
- House Extension 2012 002 (Small).JPG (103.21 KiB) Viewed 5297 times
-
- Main bedroom painted part 1
- House Extension 2012 003 (Small).JPG (105.36 KiB) Viewed 5297 times
-
- Rear bedroom all painted
- House Extension 2012 001 (Small).JPG (115.52 KiB) Viewed 5297 times
-
- Front steps in place
- House Extension 2012 004 (Small).JPG (153.95 KiB) Viewed 5297 times
-
- steps in the garage up to kitchen door
- House Extension 2012 005 (Small).JPG (132.44 KiB) Viewed 5297 times
-
- soil in place for ensuite connection
- House Extension 2012 007 (Small).JPG (138.75 KiB) Viewed 5297 times
-
- Soil for downstairs wc
- House Extension 2012 008 (Small).JPG (153.63 KiB) Viewed 5297 times
-
- Pipework in place ready for the en suite
- House Extension 2012 009 (Small).JPG (129.9 KiB) Viewed 5297 times
-
- Alarm PIR in place
- House Extension 2012 010 (Small).JPG (99.21 KiB) Viewed 5297 times