Fitting new bathroom suite - Tile before or after fitting ba
Moderator: Moderators
-
- Senior Member
- Posts: 426
- Joined: Sun Jul 12, 2009 10:22 am
- Location: Wales
- Has thanked: 75 times
- Been thanked: 3 times
Fitting new bathroom suite - Tile before or after fitting ba
hi
Do i tile walls before i fit the bath/shower ? Do i need to go below the lip of the bath or do i tile later onto it ??
Same with shower, i need to stud out a section just for this to fit pipes behind. How do i go about it ??
Cheers
Do i tile walls before i fit the bath/shower ? Do i need to go below the lip of the bath or do i tile later onto it ??
Same with shower, i need to stud out a section just for this to fit pipes behind. How do i go about it ??
Cheers
- wine~o
- Senior Member
- Posts: 26279
- Joined: Sat Jan 10, 2009 3:49 pm
- Location: hants/dorset border
- Has thanked: 1414 times
- Been thanked: 4019 times
Re: Fitting new bathroom suite - Tile before or after fittin
Your bath will need fixing to the wall..unless freestanding...
I'd be looking at tiling After fitting the bath.(and no point tiling under the bath if it's fitted properly)
..but before fitting the shower..
HTH
I'd be looking at tiling After fitting the bath.(and no point tiling under the bath if it's fitted properly)
..but before fitting the shower..
HTH
Verwood Handyman
_____________________________________________________________________________
If you feel you have benefited from the Free advice given on the Forum, Please consider making a donation to UHM's Nominated charity, read all about it and donate here :
http://www.donnasdreamhouse.co.uk
_____________________________________________________________________________
If you feel you have benefited from the Free advice given on the Forum, Please consider making a donation to UHM's Nominated charity, read all about it and donate here :
http://www.donnasdreamhouse.co.uk
- fred99
- Senior Member
- Posts: 241
- Joined: Sun Jan 24, 2010 7:36 pm
- Has thanked: 9 times
- Been thanked: 6 times
Re: Fitting new bathroom suite - Tile before or after fittin
With baths I always tile to a batten about 3/4 tile height above the bath, then fit the bath, half fill with water, silicone between the bath and the wall, then tile down to the bath leaving a couple of mill gap for a nice neat silicone finish.
With showers I always fit the tray first and the pipework for the mixer (capped off) then tile,then fit the enclosure, mixer, riser etc.
With showers I always fit the tray first and the pipework for the mixer (capped off) then tile,then fit the enclosure, mixer, riser etc.
-
- Senior Member
- Posts: 518
- Joined: Fri Sep 25, 2009 6:09 pm
- Has thanked: 5 times
- Been thanked: 23 times
Re: Fitting new bathroom suite - Tile before or after fittin
as fred has said fit bath to wall/walls with brackets fill and seal, leave overnight.
as for battens.. yes you can use these.. but only if your "not" tanking your "wet areas"
as for the studding out measure where your pipe feed is coming thro onto ur plasterboard/backerboard and cut hole out with stanley blade/core cutter.
for tiling get the bath LEVEL..then mark out your wall for tile fixing..at least half a tile running off the top of bath,but check cuts onto floor and up at ceiling and corners, if not happy with size of cuts,then adjust vertical and horizontal lines on wall/walls.
as for battens.. yes you can use these.. but only if your "not" tanking your "wet areas"
as for the studding out measure where your pipe feed is coming thro onto ur plasterboard/backerboard and cut hole out with stanley blade/core cutter.
for tiling get the bath LEVEL..then mark out your wall for tile fixing..at least half a tile running off the top of bath,but check cuts onto floor and up at ceiling and corners, if not happy with size of cuts,then adjust vertical and horizontal lines on wall/walls.
-
- Senior Member
- Posts: 426
- Joined: Sun Jul 12, 2009 10:22 am
- Location: Wales
- Has thanked: 75 times
- Been thanked: 3 times
Re: Fitting new bathroom suite - Tile before or after fittin
Awesome info guys, would never of thought of filling bath for it to settle. It is a standard bath not freestanding.
So just leave enough room to fit a 3/4 tile at bath, i was going to just put a full tile at bath edge and tile up, i am not going all way to ceiling, just partial tiling wet areas inc above sink etc.
Cheers
Also the bath suit has an option for steel or acrylic bath, which is better peeps ????
It is for rented accom and the screfix suite for £180 !!
So just leave enough room to fit a 3/4 tile at bath, i was going to just put a full tile at bath edge and tile up, i am not going all way to ceiling, just partial tiling wet areas inc above sink etc.
Cheers
Also the bath suit has an option for steel or acrylic bath, which is better peeps ????
It is for rented accom and the screfix suite for £180 !!
- thescruff
- Senior Member
- Posts: 49685
- Joined: Mon Mar 10, 2008 12:46 am
- Location: Bath
- Has thanked: 360 times
- Been thanked: 3735 times
Re: Fitting new bathroom suite - Tile before or after fittin
Acrylic, will probably end up with fag burns etc, and steel will end up chipped.
Never install a bath if you intend to let.
Never install a bath if you intend to let.
- thescruff
- Senior Member
- Posts: 49685
- Joined: Mon Mar 10, 2008 12:46 am
- Location: Bath
- Has thanked: 360 times
- Been thanked: 3735 times
Re: Fitting new bathroom suite - Tile before or after fittin
If it was my choice I would go for the steel bath, they will last a bit longer.
-
- Senior Member
- Posts: 426
- Joined: Sun Jul 12, 2009 10:22 am
- Location: Wales
- Has thanked: 75 times
- Been thanked: 3 times
Re: Fitting new bathroom suite - Tile before or after fittin
Cheers guys i have ditched the tiles as i have come across a cheap lot of the 25cm plastic panel (4 in pack)
So i fit bath first and panel to top of bath. Rather than run panel on wall behind bath then fit bath later ?
Cheers
So i fit bath first and panel to top of bath. Rather than run panel on wall behind bath then fit bath later ?
Cheers
- thescruff
- Senior Member
- Posts: 49685
- Joined: Mon Mar 10, 2008 12:46 am
- Location: Bath
- Has thanked: 360 times
- Been thanked: 3735 times
Re: Fitting new bathroom suite - Tile before or after fittin
Yes that way you can seal the bath, fit the panels and give the bath a second seal.
- Crooksey
- Senior Member
- Posts: 642
- Joined: Sun Jan 03, 2010 3:16 pm
- Has thanked: 0
- Been thanked: 72 times
Re: Fitting new bathroom suite - Tile before or after fittin
I would go for plastic, mainly as if it gets damaged you can keep deposit and get a new plastic bath for under £30, easy to fit and remove.
Steel baths are a pain in the arse and even if they get damage will be even more of a pain to re-fit.
Steel baths are a pain in the arse and even if they get damage will be even more of a pain to re-fit.
- edcam
- Newly registered Member
- Posts: 6
- Joined: Sun Aug 15, 2010 8:47 pm
- Has thanked: 0
- Been thanked: 1 time
Re: Fitting new bathroom suite - Tile before or after fittin
fit the bath first to the wall make sure you spread the weight on 2 boards under feet, half fill bath with water, silicone around the bath, then tile and silicone around bath again, this gives you 2 water barriers, do the same for the shower.
-
- Senior Member
- Posts: 134
- Joined: Mon Sep 17, 2007 3:50 pm
- Has thanked: 4 times
- Been thanked: 1 time
Re: Fitting new bathroom suite - Tile before or after fittin
I would agree with what was said before but I also always use a bath sealing strip behind the last tile over the bath or shower tray.