4 weeks for plaster!

Posted: Sat Mar 27, 2010 5:45 pm
by uhoh!
I was just about to proceed with tiling when i read some info on the Bal Blue Star adhesive tub saying that plaster needs 4 weeks (4 weeks!) before tiled over. I've made patch repairs from where the previous tiles were taken off, do I really have to wait 4 weeks (4 weeks!) before I can tile over there???!

How bad can it be?! Does everyone do this?

:?

Posted: Sat Mar 27, 2010 8:09 pm
by marc1106
no the 4 weeks is usually for a bond and set wall as its the bonding that takes the tme to cure , but if you have just skimmed or patched in then 2-3 days should be fine! just remember to prime the walls with an acrylic primer first! cant remember if bluestar has a built in primer or not, should say on the tub! :thumbright:

Posted: Sat Mar 27, 2010 10:25 pm
by tictic
marc is correct,and the bal blue star has the primer already in it. :thumbright: