I was just about to proceed with tiling when i read some info on the Bal Blue Star adhesive tub saying that plaster needs 4 weeks (4 weeks!) before tiled over. I've made patch repairs from where the previous tiles were taken off, do I really have to wait 4 weeks (4 weeks!) before I can tile over there???!
How bad can it be?! Does everyone do this?
4 weeks for plaster!
Moderator: Moderators
-
- Senior Member
- Posts: 824
- Joined: Tue Jul 15, 2008 10:15 pm
- Location: on my computer (obviously)
- Has thanked: 4 times
- Been thanked: 49 times
no the 4 weeks is usually for a bond and set wall as its the bonding that takes the tme to cure , but if you have just skimmed or patched in then 2-3 days should be fine! just remember to prime the walls with an acrylic primer first! cant remember if bluestar has a built in primer or not, should say on the tub!